Ford Siyerra + 1.2. Car identification + 2. Maintenance + 3. General data + 4. Engines + 5. Coupling + 6. Transmissions + 7. Driveshaft and back bridge + 8. Steering + 9. Suspension brackets + 10. Brake system + 11. Body - 12. Electric equipment 12.1. Technical characteristics 12.2. Relay and safety locks 12.3. Removal and generator installation 12.4. Dismantling and generator assembly 12.5. Adjustment of a tension of a maple belt 12.6. Starter 12.7. Windscreen screen wiper, knot of indexes and headlight 12.8. Removal and installation of a combination of devices 12.9. Adjustment of light of headlights - 12.10. Heating and ventilation system 12.10.1. Removal and heater installation 12.10.2. Fan engine + 12.11. Electroschemes
|
System of heating and car ventilation
|
1–heater,
2–case of a heater,
3–air zaslonka,
4–knot of management,
5–case of the fan,
6–fans
|
Heater case
|
1–nut of fastening,
2–heater,
3–bells of supply of air
|
Removal
PERFORMANCE ORDER |
1. To disconnect a weight wire from the accumulator. |
2. In a compartment of the engine to establish spring clips on the elastic pipelines of cooling liquid connected to a heater. |
3. To disconnect a cover and consolidations of air pipelines. |
4. To remove the average console of the forward panel together with a ware box (fastening by six bolts). |
5. To remove control lever brackets heating on the forward panel and to unscrew the control lever case (three screws), to move it down and to disconnect electric wires. |
6. To disconnect from heating knot air bells. |
7. To disconnect on the left side two cables of management of supply of air. |
8. To unscrew nuts of fastening of knot of heating and to take it. |
|
Installation
PERFORMANCE ORDER |
For installation of knot of heating it is necessary to execute actions in return sequence in relation to removal process. Before installation of facing of a floor it is necessary to adjust a cable of management of supply of air. After installation of a heater it is necessary to remove air from system of cooling of the engine and to fill amount of cooling liquid to necessary level. |
|
|
|